|
STOCKDALE MILL
|
STOCKDALE MILL RESTORATION
The mill was purchased in November, 2001 from the Krom (Deck) family. Attention was first given to the concrete and wooden beam foundation. Next the stuctural beams were aligned. The roof (severely damaged in a January 2002 storm) was replaced. The siding of the structure has been restored to the original form. Windows were reworked, and screens were installed over the duct exits.
A new roof was placed on the office area and the floor was replaced. The weigh shed was firmed-up, doors were rebuilt, and the roof replaced. Access ramps have been added. The supply shed to the north of the mill was reinforced and resided. The steel corn bin was firmed-up and painted.
A temporary coffer dam was placed
to divert the river from the mill in order to access the race and sub-basement
for cleaning and repair.
Reinforcing cement walls have been poured inside of the turbine and race areas
as well as at the parapet at the north end of the dam.
The 3 turbines were removed and rebuilt. The turbines were reinstalled in April
2003.
On September 5, 2003 all three turbines were spinning once again after being
silent for over 30 years.
The milling machinery is being cleaned
and refurbished.
New electrical
service has been being installed for lighting and maintenance.
The all floors
have seen new oak flooring installed.
Landscaping is progressing.
Stone-ground cornmeal and stone-ground whole-wheat flour produced by water power
have been reintroduced.
A "Welcome Center" has been added
in the former supply shed.
Restroom facilities have been built.
A telephone cable marring the view from the bridge has now been relocated by the phone company.
The main line shaft for the flour milling equipment is once
again active, being powered by two water turbines.
The large wooden pulleys for this shaft have been
restored.
The four large roller mill machines on the main floor are once again in position
and active.
New belting drives the equipment in the basement and main floor.
The 65 foot belt that transferes power from the basement line shaft to the line
shaft at the top of the
second floor has been installed making the second
floor shaft operational.
Belting now transfers power to the top floor (up to the peak of the roof !).
The "receiving seperator" (wheat cleaner, fanning mill) is running.
The office has been insulated and new ceiling, walls, flooring
installed.
External lighting is installed.
Twelve bucket elevators are being reconstructed. The wooden "legs" have been lifted and the "heads" aligned with the power shaft at the peak of the top floor. Wooden "boots" have been reconstructed and fitted at the bottoms of the elevators in the basement. Two of the elevators are currently operating.
The flour packer has been partially restored.
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
We have been blessed with people from the community assisting in unbelievable ways to restore the mill. So much of the material used to repair and rebuild the structure as well as thousands of hours of labor have been donated .
- prior to restoration -
Volunteers are actively
working on the building, dam & race, milling equipment, and property.
Also volunteers conduct tours, relate history, do historical research, and develop
promotional materials.
BE A VOLUNTEER !
Volunteer work days for 2005: Most Mondays and Tuesdays beginning March 29 through October.
MILESTONE
4:45PM, September 5, 2003
Water below the mill surged and churned. Muck and debris bubbled up from the
turbine discharge. Immediately the turbine began picking up speed. Hooray! The
gates had just been opended to allow water into the turbine. The mill came to
life for the first time since 1964. Soon it was joined by the other two turbines,
all
![]() |
| A Saturday tour group views water rushing in the race. |
running smoothly at about 80 rpm with a low hum. The race was now a rush of water headed for the turbines and out to the river below.
This was the culmination of a tremendous amount of work by mill volunteers. First the installation of the coffer dam, the removal of mud from the race and flume, removal of the turbines, concrete work in the race and flume, reconstruction of turbine parts, rebuilding the turbines, placing and aligning the turbines back in place, reworking the gate controls, reconstructing and fitting the debris grates, and finally removing the coffer dam to let the water in. All present were suprised by how perfectly the turbines were running and how responsive they were to the gate controls. Congratulations to all who had a hand in providing this to the community.
Although the turbines seemed to be begging for work, no load was available for them. All belts and line shaft gears have been pulled back, these await further reconstruction before use.